Project description:
Construction of a chemical (containerized) test and pilot plant in accordance with the customer's process and procedure specifications.
Scope of the order: basic and detailed engineering, delivery, assembly and commissioning.
The methanation plant is part of the Energy Lab 2.0 and represents a possible link for the temporary storage of renewable energies in the natural gas network.
The plant is used to convert synthesis gas (using a catalytic process) into a methane-containing product.
Scope Frintec GmbH:
- Installation planning (3D CAD planning)
- Pipe planning and design
- Position, data sheets, lists and specifications
- Construction, delivery and assembly of the entire system
- Commissioning and acceptance
Technical data:
- Flow 50 m³/h
Project period:
2018 to 2019