Conversion to 3-phase methanation

Conversion to 3-phase methanation

Project description:

A return system will be integrated into the existing three-phase methanation system in the Energy Lab 2.0 and gas will be circulating using a compressor.


Scope of Frintec GmbH:

- Installation planning (3D CAD planning)

- Pipe planning and design

- Position, data sheets, lists and specifications

- Construction, delivery and assembly of apparatus and pipelines

- Commissioning and acceptance


Technical data:

- Pressure 30 bar

- Temperature 350°C

- Flow 50 m³/h

Project period:

2022 to 2023


 



back to projects