Project description:
A return system will be integrated into the existing three-phase methanation system in the Energy Lab 2.0 and gas will be circulating using a compressor.
Scope of Frintec GmbH:
- Installation planning (3D CAD planning)
- Pipe planning and design
- Position, data sheets, lists and specifications
- Construction, delivery and assembly of apparatus and pipelines
- Commissioning and acceptance
Technical data:
- Pressure 30 bar
- Temperature 350°C
- Flow 50 m³/h
Project period:
2022 to 2023